A Türi School project in Estonia is a good example of that – substantially different from a lot of IST Engineering’s projects, and yet performed with the same level of attention and professionalism. This project was completed in the years 2019-2020, and it only took 4 weeks in total to produce all of the necessary parts for the building itself.
It is worth noting that, while there was a long list of trusses, beams and other connections made by IST Engineering, this was the only operation that was requested. IST Engineering’s construction services were not needed in this case – despite the long history of both producing carbon steel building parts and constructing all kinds of warehouses and other facilities. The total weight of the collective parts that were produced was estimated at 58 tonnes.